← All Insights Lost in hole: one stuck assembly, two documents, and a $1.48 million dispute. Lost-in-hole clauses in drilling contracts, Vermeulens
Drilling Contracts

Lost in Hole: One Stuck Assembly, Two Documents, and a $1.48 Million Dispute

Olga Labai, Of Counsel / Senior Legal Counsel · 24 November 2026 · 7 min read

What lost-in-hole clauses decide about responsibility, value and time charges

In December 2017, drilling equipment became stuck in a well in West Virginia. The operator tried to fish it out, then decided to plug the well. The service provider sent an invoice for the equipment. The operator refused to pay, pointing to the master services agreement (MSA). The provider pointed to its proposal, which contains lost-in-hole prices and terms.

That is the short version of Antero Resources Corporation v Directional One Services. The two lost-in-hole events happened on separate wells. The invoices were $762,425.30 and $719,085.00. The circuit court entered judgment for $1,481,510.30, plus interest, and the Supreme Court of Appeals of West Virginia affirmed.

The fight was not over whether equipment had been lost. It was over what the parties’ documents said should happen when it was.

In its refusal to pay, the operator stated that the master services agreement puts the risk on the supplier. The supplier pointed to its proposal and rate sheets, which listed lost-in-hole prices, set out a choice between fishing and paying for lost equipment, and offered an extra fee to reduce the operator’s liability.

The documents had been used together for years. The operator had previously paid lost-in-hole invoices and bought the liability-reduction option on other wells. But for this well, it had stopped paying for that protection.

The West Virginia Supreme Court upheld a total award of about $1.48 million to the supplier, reading the master agreement and rate sheets together. Two justices disagreed. They said the master agreement’s conflict clause controlled and left the risk with the supplier. Same wells. Same documents. Different reading of what the parties had agreed to. The court records show how a lost-in-hole dispute can trigger the scrutiny over the relationship between a master agreement, a rate sheet and the parties’ decisions over time.

That case is a useful place to begin because “lost in hole” is often treated as a line item: the tool gets stuck, someone pays a stated price, and the job moves on. At the wellsite, the decision is rarely that neat. Do you keep fishing? Who directs the operation? When do rental charges stop? If the tool comes back damaged, who decides whether it can be repaired? And if the supplier’s equipment failed, does the same payment rule still apply?

Here are six things the contract needs to settle.

1. Two documents can make one contract

Directional One’s proposal had three parts: daily rates, replacement prices for lost-in-hole equipment, and general terms. The master services agreement, drafted by Antero, referred to Directional One’s published rate schedule for pricing. It also said that the MSA controlled over conflicting terms in a published rate schedule or another document.

That sounds like a clear hierarchy: one over another. But the majority read the two documents together and found that the MSA depended on the rate sheets for pricing and the details of the work and concluded that the proposal’s more specific terms “qualified” the MSA. The parties’ history mattered too: for several years, Antero had paid invoices for damaged and lost equipment and had elected to pay for a lost-in-hole liability reduction.

The dissent saw the same documents differently. It considered the MSA’s conflict clause decisive: the proposal supplied prices, but its conflicting risk-allocation terms could not override the MSA’s indemnity and insurance provisions.

The disagreement is a useful warning for any services contract built from an MSA, rate schedule, proposal, purchase order and work ticket. The order of precedence, the documents incorporated, and the scope of that incorporation all matter.

2. “Lost in hole” does not answer the fault question

A lost-in-hole clause may allocate the cost by ownership, custody or control. It may make payment due regardless of fault. Or it may carve out loss caused by the service provider or its personnel. Those are different bargains.

In Antero, the dispute turned mainly on how the MSA and proposal allocated the equipment cost. A separate Trinidad and Tobago decision shows how much the causation wording can matter. In T.O.C. Ltd v Range Resources Trinidad Ltd, the drilling contract put downhole equipment loss on the operator except when the contractor or someone under its control caused it. The court found that the contractor’s breach had caused the drill string to stick and refused reimbursement for the contractor’s lost items.

The distinction is simple but consequential. A tool can be lost downhole without the contract making the supplier responsible for the loss. Whether fault changes the payment depends on the words the parties used.

3. The operator usually makes the fishing decision

The operator will commonly direct the decision whether to fish as part of managing petroleum operations. The specialist may be engaged directly or through another contractor, and the contract chain and approval authority depend on the governing agreements.

In Antero, the record described Antero as having overall supervisory authority over drilling and the sole authority to decide whether to fish or plug the well and abandon the equipment. That operational authority does not establish that every fishing contractor is hired directly by an operator. The operator may procure the specialist itself, use an existing master agreement, or engage the work through the drilling contractor. Model petroleum contracts also give operators substantial operational roles while preserving oversight and obligations at contractor-group level.

This separates two decisions that are sometimes blended together: who directs the well operation, and who is contractually responsible for the equipment bill.

4. Compensation is not always an indemnity

Lost-in-hole provisions often appear in the indemnity section, even when much of the clause is doing pricing work. It may set an equipment value, apply depreciation, impose a deductible, stop rental charges, and offer a reduced-liability option.

That raises a fair question: is indemnity the right legal mechanism to be applied for compensation for equipment? A first-party payment for the value of a lost tool does a different job from an indemnity for defined claims or liabilities. A clause may provide for one or both, but the distinction matters when the payment is read alongside the liability cap, insurance obligations, knock-for-knock provisions and exclusions for downtime or other losses.

Antero’s MSA required Directional One to carry property insurance and contained indemnity language. The proposal separately priced lost-in-hole equipment and offered an optional liability-reduction arrangement. Antero had elected that option on earlier wells, then stopped before the two disputed incidents. The majority treated that history as part of the parties’ contractual arrangement; the dissent considered the MSA’s written terms controlling.

That is the practical tension. An equipment price, an insurance obligation and an indemnity can sit in the same contract package without doing the same work.

5. The equipment value can become a second dispute

A price list gives the parties a number, but it does not always settle how that number was reached. Is it replacement cost, landed cost, depreciated value or a negotiated lost-in-hole price? Does the calculation change if the tool is repairable, damaged beyond repair or only partly damaged?

After an incident, one side may say, “we can repair it”; the other may say, “it’s scrap”. They may disagree about the repair bill, too. Purchase records, equipment history, repair estimates and a stated depreciation method give the parties something concrete to work from.

The Antero dispute also involved invoices, prior payments, the optional liability reduction and the two specific lost assemblies. Those details mattered to the court’s reading of the overall arrangement. The written documents were central, but the parties’ conduct over time became part of the analysis.

6. The timing affects the account

The operational event and the billing event may not happen at the same time. A tool becomes stuck. Fishing attempts follow. The operator may later declare it lost or decide to plug the well. The contract may stop rental charges from the first event, from written confirmation, or only after a specified decision.

A later retrieval creates another question. Do charges resume if the equipment is recovered and used again? Is compensation adjusted? Who owns the tool? These details can change the final account even when everyone agrees about what happened downhole.

The wellsite record is often what fixes the timeline: daily drilling reports, tool records, incident notices and fishing reports. In Antero, the earlier invoices and the parties’ prior elections over lost-in-hole liability reduction helped shape the court’s view of the relationship between the two documents.

A stuck assembly is an operational problem. An invoice for its loss becomes a contract dispute when the MSA, proposal, indemnity and pricing provisions point in different directions. The lesson from Antero is not that a rate sheet always prevails, or that an MSA always prevails. The conflict over the compensation can become a quest on how the documents fit together, what the parties did before the loss, and the precise risk they agreed to carry.